Mayfair Gold Provides Update on Project Work in the First Quarter of 2026 Advancing and Derisking the Fenn-Gib Gold Project
"The progress achieved in the first quarter reflects the disciplined, methodical approach we are taking as we advance and derisk the Fenn-Gib Gold project through the permitting process toward development. Each workstream is moving forward with clarity and purpose, and as the team grows, we continue to deliver the technical foundations required for a successful build," said
The aspects of the work advance in Q1 2026 include the following:
Compilation of Environmental Baseline Study work
Throughout Q1 2026, the Company advanced the integration and interpretation of the multi‑year environmental baseline studies initiated in 2023. Work this quarter focused on advancing and consolidating studies concerning fish and fish habitat, hydrology, hydrogeology, geochemistry, wildlife, and vegetation into technical packages to support the upcoming application into
Notification of Project Status
The Company submitted the Notification of Project Status ("NPS") during the first quarter signalling the intent to advance the project into production and is now awaiting formal guidance and next‑step requirements from the
Environmental Assessment
In the first quarter, the Company awarded the EA and permitting mandate to
Highway 101 Realignment
Work commenced in late Q1 on the environmental assessment process for the proposed
Advancement of Site Investigations and Site Drilling
During the quarter, the Company advanced expanded site investigation programs. Geotechnical fieldwork resumed in early 2026, advancing work initiated in 2025, for the proposed tailings storage facility ("TSF"), site infrastructure areas, and the process plant. In parallel, condemnation drilling commenced across priority infrastructure zones to confirm the absence of mineralization and delineate the final site layout.
The Company also advanced pump testing activities to strengthen the understanding of groundwater conditions across the project area. These tests provide information on sub-surface water characteristics, hydraulic conductivity, and groundwater flow responses under sustained pumping that is vital to ongoing site engineering. The results will be incorporated into updated hydrogeological models to refine predictions of pit dewatering requirements, assess potential interactions with nearby water bodies, and support EA and permitting submissions.
Front-End Engineering and Design ("FEED") Initiated with Ausenco
In the first quarter, the Company commenced Front-End Engineering and Design (FEED) with Ausenco Engineering for the planned 4,800 tpd processing facility. This phase of work includes completing applicable financial trade‑off studies, advancing Process Design Criteria (PDC) and Piping and Instrumentation Diagrams (P&ID) to formalize Project design and will support advancing into detailed engineering in the second half of 2026. Q1 FEED activities focused on refining the comminution circuit and flotation layouts, integrating outcomes from third‑party reviews, and establishing the engineering basis to support continued advancement of the plant design.
Next Steps
The first quarter of 2026 also allowed the Team to advance the planning and coordination of the following work:
Metallurgical Testing
To support comminution circuit design and establish additional data for rock competency characterization, large‑diameter diamond drill core will be collected to generate expanded A×b rock hardness data. These results will refine parameters and inform equipment sizing and energy requirements for the operating plant. In parallel, follow‑on work from the tailings settlement testing program completed in Q1 will be undertaken to better define the settled density of tailings material within the TSF.
Advancing the Mineral Resource Estimate drilling program
In the first quarter, all remaining assays from the 2025 Mineral Resource Estimate (MRE) confirmation drilling program were received. With the full 2025 MRE confirmation dataset now complete, the geology team, together with the Mineral Resource Qualified Person, are advancing the development of an updated localized model and evaluation of preliminary ore block designs within the area drilled. Upon completion, the updated local model will be compared against the MRE used in the Pre‑Feasibility Study (PFS) to assess changes in grade distribution, geological continuity, and provide insight into any variability on future mine planning and operational predictability.
Ongoing Site Investigations and Geotechnical Programs
Site investigation activities will continue through the second quarter, including additional geotechnical drilling, test pitting, and material characterization across the TSF, plant site, and infrastructure locations. These programs will further refine foundation design parameters and support the advancement into the detailed engineering phase.
The Company along with TWD Engineering are advancing work to define the preferred power‑to‑site solution, including evaluation of transmission routing and supply voltage, interconnection requirements, and technical specifications. Engagement with the relevant utilities and regulatory bodies including Hydro One Network ("HONI") and the
Open Pit Geotechnical Drilling
Additional open pit geotechnical drilling is to commence in the third quarter. Initial geotechnical work completed in 2023 supported the open pit designs developed for the PFS. Building upon this foundation, the program will gather supplementary structural, geomechanical, and hydrogeological data to enhance the accuracy of open pit slope designs and facilitate pit optimization and operational stability evaluations.
Mayfair is growing the core team to advance Fenn-Gib and support the ongoing initiatives to derisk the Project, support the Provincial permitting process and make preparations in advance of the start of construction.
Advertising Service Agreement
The Company also announces it has entered into a service agreement with
About
The content of this news release has been reviewed on behalf of the Company and approved by
Cautionary Note Regarding Forward-Looking Information
This news release contains certain forward-looking information and forward-looking statements within the meaning of applicable securities legislation (collectively "forward-looking Information"). The use of the words "will" and "expected" and similar expressions are intended to identify forward-looking information. This information includes statements regarding the scope, timing and expected outcomes from future workstreams. Although Mayfair Gold believes that the expectations reflected in such forward-looking statements and/or information are reasonable, readers are cautioned that actual results may vary from the forward-looking information. The Company has based these forward-looking statements and information on the Company's current expectations and assumptions about future events. This information also involves known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking information, including the risks, uncertainties and other factors identified in the annual information form of the Company for the year ended
Neither the
View original content to download multimedia:https://www.prnewswire.com/news-releases/mayfair-gold-provides-update-on-project-work-in-the-first-quarter-of-2026-advancing-and-derisking-the-fenn-gib-gold-project-302754876.html
SOURCE