ACLARA ANNOUNCES UPDATED PEA FOR ITS FLAGSHIP CARINA MODULE
After-tax NPV
8
of
After-tax NPV 8 of US$ 2 . 2 billion using incentive price forecast (excluding Chinese supply)
The technical report titled "Preliminary Economic Assessment Update - Carina Rare Earth Element Project -
Highlights
- Robust economics
-
- After-tax Net Present Value ("NPV") of
~US$1.5 billion using an 8% discount rate pursuant to the base case price forecast projected by Argus Media ("Argus") - 27% internal rate of return over the 22-year life of mine and a payback period of 4.2 years
- Low initial capital costs of
US$593 million and low sustaining capital costs ofUS$86 million - Average annual1 net revenue and EBITDA of
US$505 million andUS$366 million , respectively - High average net smelter return ("NSR") of
US$52.0 per tonne processed compared to a low average production cost ofUS$13.6 per tonne processed - Incentive price forecast scenario projected by Argus provides significant upside. This scenario is supported by critical raw material regulations such as the European Critical Raw Materials Act and the United States Inflation Reduction Act, which focus on creating supply chains beyond
China - After-tax NPV of
~US$2.2 billion using an 8% discount rate pursuant to the incentive price forecast by Argus (which excludes Chinese supply)
- After-tax Net Present Value ("NPV") of
- Significant production of magnetic REEs and high product quality
-
- Average annual production1 of 191 tonnes DyTb representing approximately 13% of
China's 2023 official production2
- Average annual production1 of 191 tonnes DyTb representing approximately 13% of
_________________________________ |
1 Annual average does not consider the first year of ramp-up and the last year of ramp-down. |
2 The resulting Chinese production of DyTb derived from its 2023 rare earth oxides quotas for mining production is approximately 1,520 tonnes (source: |
-
- Average annual production1 of 1,350 tonnes NdPr contributing to a balanced mix of light and heavy REEs in the final product
- Very high content of DyTb and NdPr in the mixed carbonate of 4.0% and 28.5%, respectively
- Concentration of REEs in the mixed carbonate of 91.5%3. High purity product facilitates further separation and recoveries
__________________________________ |
3 Purity is expressed as REO equivalent. |
- Expedited path to early production
-
- Memorandum of Understanding signed with the
State of Goiás and Nova Roma Municipality inBrazil to accelerate the analysis and evaluation of the permitting process and implementation of the Carina Module - Commissioning estimated to commence in 2029. The Company is evaluating the possibility to expedite the production schedule to begin between 2027 and 2028
- Memorandum of Understanding signed with the
- Low environmental impact
-
- Process designed to minimize environmental impact: it does not use explosives; there is no crushing nor milling; approximately 95% of the water used is recirculated; the main reagent is a common fertilizer; no liquid residue is produced, negating the need of a tailings dam
- Minimal CO2 footprint is supported by a combination of low energy consumption and a high percentage of renewable energy within the
Goiás power grid
- Upside potential
-
- Exploration potential for lateral expansion to the east of the Carina Module as a result of recently secured mineral rights adjacent to the Company's existing mineral rights
- Metallurgical optimization program projected to commence in Q4 2024 will serve as additional inputs for a prefeasibility study of the Carina Module and to form the basis for a new piloting operation scheduled for Q2 2025
- Strong financial backing
- Key shareholders in
Eduardo Hochschild and Hochschild Mining provide financial support to advance the Project - Strategic partnership with CAP S.A. in its Chilean subsidiary derisks project financing for the Penco Module and allows Aclara to focus incremental corporate resources to the Carina Module
- Strong bedrock for vertical integration
-
- Adds to the Company's Penco Module production of DyTb for a total DyTb annual average production1 of 241 tonnes, which represents 16% of
China's 2023 official DyTb production - Mixed REE carbonate produced expected to be separated and converted into metals and alloys by
Aclara Technologies Inc. , the Company's US based subsidiary developing REE processing technologies - Strategic partnership signed with
VACUUMSCHMELZE GmbH & Co. KG aimed at developing a mine to magnet solution
- Adds to the Company's Penco Module production of DyTb for a total DyTb annual average production1 of 241 tonnes, which represents 16% of
Ac
l
ara'
s
CEO,
"
The PEA highlights the Carina Module
's notable economic potential, with an after-tax NPV of US
T he medium to long -term outlook for rare earth elements, particularly heavy rare earths, remain s strong due to their global scarcity. Increasing international regulations are enhancing the development of alternative supply chains beyond China, and Argus's incentive price forecast indicates substantial upside potential for rare earths in response to future demand.
Our focus is now on expediting the path to early production. We have recently signed a Memorandum of Understanding with the
Table 1 and Table 2 list the relevant parameters associated with the Project's operating and financial metrics as compared to the previous preliminary economic assessment filed on
- 25% increase in after-tax NPV from
US$1.2 billion toUS$1.5 billion using an 8% discount rate, despite lower REE price forecast - Slower growth of magnetic REE4 prices following the short-term deacceleration of electric vehicle demand compared to the Previous PEA. In addition, lower expected increase in Nd price, partially offset by higher expected increase in Dy price compared to the Previous PEA. REE price forecast provided by Argus aligns well with global supply/demand fundamentals.
-
- Nd price compound annual growth rate 2023-2034: PEA 7% vs. Previous PEA 10%
- Dy price compound annual growth rate 2023-2034: PEA 12% vs. Previous PEA 11%
- ~30% increase in life of mine from 17 years to 22 years provides support for potential capacity increases in the future
- Total capital costs (initial capital costs and sustaining capital costs) maintained at the same level as prior estimates
Table 1: Key Project Operating Parameters Compared to Previous PEA
|
|
PEA |
Previous PEA |
||
|
Unit |
Total |
Annual |
Total |
Annual |
Mining and Processing |
|
|
|
|
|
Life of Mine |
years |
22 |
- |
17 |
- |
Total Process |
million tonnes (dry) |
203.0 |
9.6 |
149.5 |
9.6 |
Total Waste Mined |
million tonnes (dry) |
64.2 |
3.0 |
43.3 |
2.6 |
Strip Ratio |
- |
0.3 |
0.3 |
0.3 |
0.3 |
Production |
|
|
|
|
|
Total Rare Earth Oxides |
tonnes |
99,931 |
4,736 |
70,307 |
4,498 |
Neodymium & Praseodymium (NdPr) |
tonnes |
28,514 |
1,248 |
18,546 |
1,190 |
Dysprosium (Dy) |
tonnes |
3,420 |
163 |
2,802 |
178 |
Terbium (Tb) |
tonnes |
587 |
28 |
479 |
30 |
*Note: Annual average does not include the first year of ramp-up and the last year of ramp-down |
__________________________________ |
4 Magnetic REE include Neodymium (Nd), Praseodymium (Pr), Dysprosium (Dy) and Terbium (Tb). |
Table
2
:
|
|
PEA |
Previous PEA |
||||
|
|
Base Case (Chinese Prices) |
Incentive Case (Non-Chinese Prices) |
Base Case (Chinese Prices) |
|||
|
Unit |
Total |
Annual |
Total |
Annual |
Total |
Annual |
Financials |
|
|
|
|
|
|
|
Net Revenue |
US$ million |
10,554 |
505 |
13,091 |
626 |
7,355 |
474 |
Net Smelter Return |
US$/t |
52.0 |
- |
64.5 |
- |
49.2 |
- |
Basket Price (2029-2034) |
US$/kg |
88.8 |
- |
104.6 |
- |
107.4 |
- |
Basket Price (LOM) |
US$/kg |
122.4 |
- |
142.8 |
- |
121.2 |
- |
Production Cost |
US$ million |
2,757 |
129 |
2,757 |
129 |
1,965 |
125 |
Unit Cost |
US$/t processed |
13.6 |
- |
13.6 |
- |
13.1 |
- |
Unit Cost |
US$/kg REO |
27.6 |
- |
27.6 |
- |
27.9 |
|
EBITDA |
US$ million |
7,586 |
366 |
10,072 |
485 |
5,243 |
340 |
EBITDA Margin |
% |
72 |
- |
77 |
- |
71 |
- |
Income Tax |
US$ million |
2,334 |
118 |
3,172 |
154 |
1,532 |
101 |
Effective Tax Rate |
% |
36.1 |
- |
35.9 |
- |
36.2 |
- |
|
US$ million |
592.6 |
- |
592.6 |
- |
575.8 |
- |
Royalty Purchase Cost |
US$ million |
6.5 |
- |
6.5 |
- |
6.5 |
- |
Sustaining Capital |
US$ million |
85.8 |
- |
85.8 |
- |
106.2 |
- |
Financial Returns |
|
|
|
|
|
|
|
Pre-Tax Net Present Value (8%) |
US$ million |
2,337 |
- |
3,051 |
- |
1,880 |
- |
Pre-Tax Internal Rate of Return |
% |
32.2 |
- |
40.5 |
- |
35.7 |
- |
Post-Tax Net Present Value (8%) |
US$ million |
1,483 |
- |
2,159 |
- |
1,186 |
- |
Post-Tax Internal Rate of Return |
% |
26.5 |
- |
33.1 |
- |
28.6 |
- |
Payback Period |
years |
4.2 |
- |
3.4 |
- |
3.6 |
- |
*Note: Annual average does not include the first year of ramp-up and the last year of ramp-down |
Sensitivity Analysis
A sensitivity analysis was undertaken to evaluate the impact on NPV through variation of the basket price, discount rate, CAPEX, OPEX and metallurgical recovery rates.
The discount rate was evaluated by varying its value from 4% to 12% while the remaining attributes were evaluated by varying their values from 80% to 120% (Figure 2).
Mineral Resource Statement
The Carina Module's mineral resources have been estimated using the results obtained from 283 auger drill holes (2,101m), 80 reverse circulation holes (2,003m) and 3,789 samples. At a
Table 3 . Carina Module Inferred Mineral Resource Estimate (Effective May 3, 2024)
Mineral Classification |
Mass (Mt) |
Total Oxide Grade (ppm) |
Oxide Content (t) |
||||||
TREO |
NdPr |
Dy |
Tb |
TREO |
NdPr |
Dy |
Tb |
||
Inferred |
297.6 |
1,452 |
284 |
39 |
6 |
432,003 |
84,565 |
11,573 |
1,897 |
Total |
297.6 |
1,452 |
284 |
39 |
6 |
432,003 |
84,565 |
11,573 |
1,897 |
Notes: |
1. CIM (2014) definitions were followed for mineral resources. |
2. Mineral resources are estimated above an NSR value of |
3. Mineral resources are estimated using average long term metal prices and metallurgical recoveries (see PEA for details). |
4. Mineral resources are not mineral reserves and do not have demonstrated economic viability. |
Project Description
The Project is based on standard open pit extraction techniques using conventional hydraulic excavators and 44t payload haulage trucks to extract and deliver the clays to the process plant. The process plant has been located close to the centre of mass of the mining operation to minimise the total haulage distance over the life of mine. Given the friable nature of the clays and the shallow depth of the extraction zones, no aggressive nor energy-intensive techniques such as drilling and blasting are required to extract the clays from the pits. Table 4 lists the key input parameters used in the mine design.
Table 4 : Key M ine D esign Parameters
Description |
Unit |
Value |
Pit Optimization |
|
|
Overall Slope Angle |
degree |
25 |
Reference |
US$/t mined |
2.13 |
Mining Recovery |
% |
98.5 |
Mining Dilution |
% |
1.5 |
Processing Cost |
US$/t processed |
10.46 |
Selling Cost |
US$/kg REO |
7.032 |
Federal Royalty |
% of revenue |
3 |
REO Price |
US$/kg REO |
variable by REO |
Pit design |
|
|
|
m |
4 |
Berm Width |
m |
3.5 |
Bench Slope Angle |
degree |
38 |
Ramp Width |
m |
12 |
Ramp Gradient |
% |
10 |
Scheduling |
|
|
Minimum Operational Area |
m |
25 |
Plant feed |
Mt/year |
9.6 |
Once the clay is delivered to the process plant, it will be washed using an ammonium sulfate solution to extract the REEs from the clay surfaces. No crushing, grinding nor milling is needed to free the REEs from the clays as they are extracted through a non-invasive ion-exchange reaction process whereby ammonium sulfate ions replace REE ions on the surface of the clay thereby liberating the REEs into solution. The REEs in solution are then removed through a pH-adjusted precipitation process and then passed through a high-pressure filter to remove any remaining liquids, resulting in the production of a high-purity REE carbonate ready for shipment to a separation facility. The process plant will have an average production rate of 4,736 t/year of REO within the concentrates.
Any unwanted impurities such as aluminium and calcium that have been extracted from the clays during the ion exchange process are similarly removed through a precipitation process and then recombined with the washed clays before being transported to a dry stacking storage facility for the first five years of the life of mine. Beginning in year 6, the washed clays will be back-filled to the mined-out extraction zones to initiate the mine closure process.
A water recovery system integrated into the process plant cleans and regenerates the remaining process liquors such that they can be reintroduced into the feed. The treated water is reused in a closed circuit to reduce water consumption thereby preventing the release of process water into the environment. This allows the process plant to operate with the minimum of make-up water and allows the main reagents to be regenerated and reused within the process plant.
Before the barren clays exit the process plant, they are washed with clean water within standard plate-and-frame filter presses. This will remove any residual ammonium sulfate from the clays before they are returned to either a dry stacking facility or used to back-fill the extraction zones to be safely used during revegetation.
The Project includes the necessary infrastructure to provide make-up water for the process plant, supply power to the site, and provide a road network to service the operation, amongst others.
Electrical power for the processing plant, truck shop, administration offices, and other facilities will be supplied by the national power utility through overhead power transmission lines from a sub-station located approximately 90 km from the project site.
REE Market Outlook and Pricing 5
Vehicle electrification, wind turbines and the transition to renewable energy sources will continue to drive demand for REEs in terms of volume and, especially, value. This will primarily affect the REEs used in alloys to fabricate permanent magnets (i.e., Dy, Nd, Pr, and Tb). The supply of clean heavy REEs, especially Dy, has become problematic because few projects target heavy REE deposits. For the medium term, the market will continue to rely on
The prices of permanent magnet REEs dropped significantly in 2023 due to a weak recovery from lockdowns in
According to Argus, there are two external factors which could have the potential to positively affect future REE prices: so-called 'green' premiums; and critical material policies (particularly within Europe and the US). Critical materials policies and regulations being enacted globally, specifically the European Critical Raw Materials Act and the United States Inflation Reduction Act, are focussed on creating raw material supply chains that are not reliant on
In an effort to account for critical raw material regulations, Argus has modelled an incentive price for magnetic rare earths, where the rare earths market effectively has a dual pricing model (Chinese and non-Chinese) that forecasts the level that REE prices would have to reach to incentivize the supply of REE from producers outside of China. Under the incentive price scenario, the forward curve for Dy grows at 15% per year, compared to 12% per year in the base case scenario (Table 5).
Table 5: Dysprosium Price Forecast
|
2022 |
2023 |
2028 |
2034 |
2023 vs
2022 |
2028 vs
2023 |
2034 vs
2028 |
CAGR
2023– |
Dy |
|
|
|
|
|
|
|
|
Base Case Price* (US$/kg) |
384 |
331 |
595 |
1,100 |
–14 |
80 |
85 |
12 |
Incentive Price (US$/kg) |
384 |
331 |
515 |
1,400 |
–14 |
56 |
170 |
15 |
Total supply (×1,000 t REO) |
1.7 |
2.6 |
3.6 |
4.4 |
50 |
39 |
23 |
5 |
Total demand (×1,000 t REO) |
2.8 |
3.3 |
5.3 |
7.0 |
16 |
62 |
32 |
7 |
Surplus/deficit index (2018 = 100) |
98 |
96 |
77 |
43 |
– |
– |
– |
– |
*99.5–99.9% fob |
The following provides an example of illustrating the potential decoupling of rare earths prices between those sourced from and outside of
_______________________________ |
5 Argus Media |
In consideration of the price forecasts provided by Argus, the basket price of the
Targeted Development Timeline
The permitting process is currently underway and the technical development of the Project will continue with a feasibility study of the Carina Module scheduled to be delivered in 2026 and commencement of operations projected to begin in 2029 (Table 6). Following the Memorandum of Understanding signed with the Government of
Proposed Next Steps
- Continuation of the Carina Module pre-feasibility study as previously reported in the Company's press release dated
May 6, 2024 - Completion of a 15,200m Phase 2 reverse circulation drill campaign aimed at converting inferred mineral resources to a measured and indicated mineral resources category, which is expected to be completed by Q4 2024
- Completion of the environmental and social baseline studies required for environmental permitting process during H2 2024
- Execution of a metallurgical test campaign during H2 2024 and H1 2025 with sample collections to be obtained through sonic drilling and sent to SGS Lakefield for mineralogical and recovery characterization, to serve as additional inputs for the Carina Module prefeasibility study and to form the basis for a new piloting operation
- The Company is aiming to complete the installation and operation of a new semi-industrial scale pilot plant in the
State of Goias, Brazil during Q2 2025. The piloting operation is intended to (i) confirm the processing parameters and the final process flowsheet design for the feasibility study, (ii) generate a high purity HREE carbonate for separation trials in support of future off-take agreements, and (iii) demonstrate to relevant stakeholders the environmental sustainability of the final process design
Qualified Person s
The technical information in this press release has been reviewed and approved by geologist Fábio Xavier, mining engineer Porfírio Cabaleiro Rodriguez, geographer and environmental analyst Mrs. Branca Horta of GE21 Consultoria Mineral Ltd., as well as Chemical Engineer Stuart J Saich of
Messrs. Rodriguez and Xavier visited the project from
Mr.
Mr. Navarro is a Member of
About Aclara
Aclara's rare earth extraction process offers several environmentally attractive features. Circular mineral harvesting does not involve blasting, crushing, or milling, and therefore does not generate tailings and eliminates the need for a tailing's storage facility. The extraction process developed by Aclara minimizes water consumption through high levels of water recirculation made possible by the inclusion of a water treatment facility within its patented process design. The ionic clay feedstock is amenable to leaching with a common fertilizer main reagent, ammonium sulfate. In addition to the development of the Penco Module and the Carina Module, the Company will continue to identify and evaluate opportunities to increase future production of heavy rare earths through greenfield exploration programs and the development of additional projects within the Company's current concessions in
Aclara has decided to vertically integrate its rare earths concentrate production towards the manufacturing of rare earths alloys. The Company has established a
Forward-Looking Statements
This press release contains "forward-looking information" within the meaning of applicable securities legislation, which reflects the Company's current expectations regarding future events, including statements with regard to, among other things, mineral continuity, grade, methodology, development timeline, production timing and upside at the Carina Module, the Company's exploration plan, drilling campaigns and activities in
View original content to download multimedia:https://www.prnewswire.com/news-releases/aclara-announces-updated-pea-for-its-flagship-carina-module-302239160.html
SOURCE